The cedar siding was completed today and the flashing on top of the cedar was almost completed. The Hardi siding is going up, its about 20% done. Inside, the furnace and hot water heater are in and we have water and a sewer connection. All sink faucets are in and working. The plumber has about two more days of work and he'll be done. The electrician has been installing outlets and switches. I finished the cabinet toe-kicks yesterday and made a lot of progress on the drawer pulls today. Noah and Les stopped by with out current neighbors the Sudworths today. It was a nice break for me from the work. Its been a lot, but I am enjoying it. I feel priviledged and blessed to be able to do it.
Thursday, May 7, 2009
Cedar Siding Finished
The cedar siding was completed today and the flashing on top of the cedar was almost completed. The Hardi siding is going up, its about 20% done. Inside, the furnace and hot water heater are in and we have water and a sewer connection. All sink faucets are in and working. The plumber has about two more days of work and he'll be done. The electrician has been installing outlets and switches. I finished the cabinet toe-kicks yesterday and made a lot of progress on the drawer pulls today. Noah and Les stopped by with out current neighbors the Sudworths today. It was a nice break for me from the work. Its been a lot, but I am enjoying it. I feel priviledged and blessed to be able to do it.
Monday, May 4, 2009
Kitchen Cabs Part 3, Countertops, and Cedar Siding
Noah loves his new tool - the level.
Here is the range hood surrounded by some custom milled side panels - done by the professional (Grandpa Bob)
This is the guest bath in the basement.
This is Noah's and Baby #2's bathroom.
'The powder room's funky little vanity.
The cedar siding started to go up on Friday and should be done some time this week. It wraps around the side of the house to the back and is looking pretty sharp.
Thursday, April 23, 2009
Kitchen Cabinetry - Part 2
Dad and Jeff have been hard at work this week and making incredible progress. The kitchen is really coming together! All of the cabinet boxes and side panels are in and they should be finished with the doors and drawers after tomorrow.
Looking from the backyard sliding doors towards the front entryway - you can even see straight out the garage door into the street.
Saturday, April 18, 2009
Kitchen Cabinetry
I'm filling in today since Jeff has been working pretty much non-stop since we got back from Florida last weekend. My dad came back down on Tuesday and they've been installing the kitchen cabinetry and doing a fantastic job! Noah and I went to visit a couple times this week to watch the men at work.
Looking from our living room area into the kitchen:
Saturday, April 11, 2009
Primer Time - Happy Easter
Thursday, April 2, 2009
Wednesday, April 1, 2009
DRY WALL!!!!
The dry wall was delivered on Monday. Due to the slow economy, we had two crews of four guys at the house yesterday and today. They were able to hang the drywall and install all the corner beads on the entire house in what seemed like no time. They plan to start taping tomorrow and could be done some time early next week. Hardwood flooring and Priming will start next week too, then Bob and I will begin to install the cabinetry when we get back from Florida.